Steps:
Set up the Contractor.
Select Setup | Vendors from the Main Menu
-
Set up the Worker.
Select Setup | Workers | Worker Setup from the Main Menu.
-
Set up Worker Base Rate. Select Setup | Workers | Worker
Base Rates.
-
Setup the Equipment Unit that the
worker is operating. Select Setup |
Equipment / Trucks | Equipment | Unit Numbers. The owner should be
different from the contractor who employs the operator and should not be your
own company. The equipment owner is the vendor to which you pay rent for
use of the machine. The equipment must also be checked as a
Rental
Unit.
-
Set up the
Hourly Rental Charge for the
Equipment. Select Setup | Equipment /
Trucks | Equipment | Equipment Charge Out Rates. This allows you to set up
the rental charge for the equipment.
-
Enter
Contractor Time Slip. Select Data Entry | Time Slips | Sub
Contractors | Enter Slips.
-
Run
Vendor (Contractor) Calculator. Select Calculators | Vendors - Full.
-
Review
Vendor (Contractor) Statement. Select Reports | Vendor
Statements | By Pay Period to review the statement for the rental equipment
owner and the contract worker. Alternatively, you can select Reports | Hourly |
Contractors to review the hourly payments for your contract worker if you
prefer this format. (The rental equipment contractor statement will
not be available in this format; this format is strictly generated for
hourly contract workers. See
Review
Vendor (Contractor) Statement - Rental equipment for an example of
the rental equipment owner statement.
Troubleshooting Common Errors:
"[1]: Error #3006: CONTRACTOR HOURLY/TREES -- PAY_CONTRACT_RATE not Set up
For: WORKER = [TEATHER]; VENDOR = [TEATHER]; ACTIVITY = [FELLER BUNCH -
THINNING] AND TIME_SLIP_DATE = [7/30/2005] Ref= [9948] " (Vendor Calculator)
This error occurs when a valid pay rate is not found for the time entry for the
contract worker for a certain date.
Things to check when this error occurs:
- Is there a pay rate set up for the worker? Check under Setup |
Workers | Worker Base Rates from the Main Menu.
- Is the effective date of the rate on or before the date for pay of the time slip
with the error? If not, the system cannot apply this rate to the time
slip.
- Check the 'Rate Type.' The Rate
Type must be set to 'HR' in order to pay hourly contractors.
2. "Error: CONTRACTOR HOURLY -- RENTAL RATE not Set up
For: EQUIPMENT = [UNIT CODE] AND TIME_SLIP_DATE = [MM/DD/YYYY] AND ACTIVITY =
[ACTIVITY CODE]". (Vendor Calculator)
This error arises because a valid rental rate is not found for the time entry for
the worker operating a rental equipment unit for a certain date.
Things to check when this occurs:
- Is there a Rental Rate setup for the equipment unit? Check under Setup |
Equipment | Equipment Charge Out Rates from the Main Menu. Be sure there is a
RENTAL rate set up in the rental rate column of the charge-out grid for the equipment unit.
- Is the effective date of the rate on or before the date of the time slip
with the error? If so, the system cannot identify a RENTAL rate to
apply to the equipment.
- Check the 'Rate Type.' The Rate
Type must be set to 'HR' in order to for the rent to be calculated.
(At present, all rental charges in the Logger's Edge are only based on
hours.)
- Does the ACTIVITY for the rental rate match the activity on the time
slip? The rental rates are Activity specific so that differential
rental rates apply to different activities. For example, you might
want to zero-rate a maintenance activity, but fully rate a production
activity. The activity on the rental rate must match the time slip, or
must be set to NONE in the rental rate grid.
- Does the REVENUE CONTRACT for the rental rate match the activity on the time
slip? The rental rates are revenue contract specific so that differential
rental rates apply to different revenue contracts. For example, you might
pay a higher rate to your contractor for the use of a piece of equipment in
connection with a customer who pays you a higher hourly rate. The
revenue contract on the rental rate must match the time slip, or must be set
to NONE in the rental rate grid.
3. The Wrong Rate is Applied.
Things to check when this occurs:
- Are there multiple rates setup for the same worker? If so, check the
effective dates to make sure you have them set up correctly.
The Logger's
Edge will use the rate that is (1)
prior to the time entry, and (2) the most recent of those that are prior to
the time entry.
- Are there multiple rates setup for the rental equipment? If so,
check the effective dates, activity, and revenue contracts on the rate
compared to your time slip to make sure that the system can pick up the rate
you intend it to pick up.