Setup: Equipment Costing
Go to Setup | Equipment/Trucks | Equipment | Equipment Costing from the Main Menu.
The grid shows two rates:
- Std Cost / Hour. This cost is the cost of operating your machine, NOT
including the cost of the operator. In reports that rely on this cost
measure, the actual cost of the operator is added to the Std Cost to
calculate the full cost of operation.
- Full Rate/Hour: This is the cost of operating your machine,
including the cost of the operator.

There are two ways to enter your costs: (1) direct entry and; (2) the
cost build-up method.
Direct Entry of Equipment Cost
Select Add from the window.

This form allows you to directly enter your equipment costs. If you
have another system to calculate your costs or you use a reference guide or
"Blue-Book" to estimate your rates, you can just enter them here.
Cost Build-up Method
The equipment cost worksheet (shown below) allows you to build up your
standard cost from each of the components. In the worksheet, the yellow
cells indicate those cells that you can enter data and assumptions. The
white cells (with numbers) are calculated values.

The worksheet is split into 5 panels:
A. Assumptions
- Annual Available Hours: Expected hours for the equipment unit for
year
- Utilization percent. The percentage of available hours the unit
performs 'production' work
- Annual Operating Hours: Calculated as the product of available
hours and the utilization percent. This value is used in the
denominator for the calculation of the average cost per hour. The
concept used here is 'cost per production hour' meaning that all costs
related to down time are allocated across production hours.
- Interest Rate on Borrowed Capital: Interest Rate on Debt
- Expected Life (Hours): Expected life (in hours) for the equipment
unit. (Used to determine the expected life of the equipment in years
for use in calculating depreciation.)
- Salvage Value: Estimated salvage value for the unit. You
enter the percent; the worksheet applies the percentage to the Purchase
Price to determine the salvage dollar amount.
- Average Investment: The average investment is the acquisition cost
plus the salvage amount divided by two [ (R16 + R11) / 2]. This is you
average capital you have tied up in the equipment unit over its useful life.
In the example above the equipment unit costs $400,000 and has a salvage
value of $100,000 (25%), which yields an average investment of $250,000.
- Purchase Price: The purchase price of the equipment. You can
also add additional miscellaneous costs to build up to a total acquisition
cost.
- Fuel Consumption (Volume / Hour): Rate of fuel consumed per hour
of operation
- Fuel Price Per Unit of Volume: The price per unit of fuel
consumed. (Note: if fuel consumption is in litres, you would enter the
litre price; if fuel consumption is in gallons, you would enter the gallon
price.)
- Machine Years: Machine life equals the lifetime hours divided by
annual hours.
- Operating Wage: Assumed base wage rate for your operator plus your
payroll load (your additional company payroll costs) cost. In the
example above, the base wage is set to $25.00/Hour and the payroll load is
set at 25% to yield an effective payroll cost of $31.25/Hr.
- Insurance (Percent of average investment): This is the cost of
insurance for the equipment unit, expressed as a percentage of you average
annual investment.
B. Ownership Cost
- Depreciation: The depreciation amount per hour equals the
depreciation basis (purchase price - salvage value) divided by the lifetime
hours. This calculation assumes a straight-line depreciation method.
[ R27 = (R16 - R11) / R10 ]
- Interest on Investment: This is the annual interest amount divided
by annual operating hours. [R28 = R12 x R9 / R8 ]
- Insurance: This is the insurance percentage multiplied by the
average investment divided by annual operating hours: [R29 = R12 x R23 / R8
]
The total hourly ownership cost equals the sum of
depreciation, interest and insurance. [R31 = R27 + R28 + R29]
C. Operating Cost
- Operating Wages: You build up your total hours as the number of
days multiplied by the average hourly work day. This total should
match the total annual estimated hours in row 6. The total hours is
then split between straight time and overtime hours. The overtime
factor is assumed to be time and one-half. This in the example above,
the wage rate is $25.00 for straight-time and $37.50 for overtime. The
hourly rates are multiplied by the available (not production) hours to calculate the annual direct
payroll cost. The loading factor is applied to the direct payroll cost
to calculate the total loaded payroll cost for the year. This total is
then divided by the production (not available) hours to calculate the operator cost per
production hour.
In the above example, the direct payroll cost is $62,500. The payroll
load is $15,625 (25% of $62,500), yielding a total payroll cost of
$78,125. The hourly cost for the operator is $32.55/Hr ($78,125
/ 2400). This value is subtracted from the full founded to cost to
compute the "Dry" or standard cost for the equipment without operator.
- Fuel Costs per Hour: This is the product of fuel consumption per
hour and fuel price per unit of consumption [R52 = R17 x R18]
- Oil and Lube, Including Filters per Hour: You input a percentage
of your fuel costs to estimate this value. In the example, the value
of 7% is entered, which when multiplied by the fuel cost per hour, yields a
value of $1.51/Hr. You can adjust this percentage to match you actual
experience.
- Repairs & Maintenance: There are three rows provided that allow
you to enter your estimated annual repairs and maintenance for the equipment
unit. The total for Repairs & Maintenance (R64 = R60 + R61 + R62) in
row 64 is then divided by annual hours to calculate the average hourly
repairs and maintenance cost. [R66 = R64 / R8]
- Operating Supplies: An annual entry for miscellaneous costs for
operating the unit. The annual amount is divided by the annual
operating hours to determine the hourly cost in row 70.
The total operating costs per hour are the sum of
operating wages, fuel, oil & lube, repairs and maintenance, and operating
supplies. [R72 = R49 + R51 + R56 + R66 + R70]
D. Profit & Risk
The worksheet also includes an allowance for profit and
risk. The allowance equals a user-input percentage applied to the hourly
ownership costs in row 29. In the example above, a 10 percent entry is
applied to an ownership cost of $250,000 for a profit/risk allowance of $13.02/hr.
E. Summary.
The total hourly operating costs are summarized in the
last section of the spreadsheet. The total hourly costs (Full Founded
Rate) are the sum of the ownership costs (row 31), the operating costs (row 72),
and profit & risk (row 77). [R85 = R31 + R72 + R77]. In the above example,
the total is $144.58/hr. This is the Full Rate / Hr and is used for those
business reports that rely on the 'Full Founded Rate' to measure equipment
costs.
The Standard Cost/Hr is also calculated by the worksheet. This cost is the cost of operating your machine, NOT
including the cost of the operator. Mathematically, it is calculated
as the total in row 83 less the operator's cost in row 49. In the example,
the cost is $144.58 less $103.89, or 56.56. In reports that rely on this cost
measure, the actual cost of your operator is added to the Std Cost to
calculate the full cost of operating the equipment unit.